[sakai2-tcc] VOTE on 2.8 timeline (SHORTENED period)

John Bush john.bush at rsmart.com
Fri Aug 20 09:07:12 PDT 2010


+1

On Fri, Aug 20, 2010 at 5:23 AM, Seth Theriault <slt at columbia.edu> wrote:
> May, Megan Marie wrote:
>
>> The schedule for 2.8 release activity has been updated to
>> reflect comments collected as well as the discussion from
>> Wednesday.
>>
>> It is available at
>> http://confluence.sakaiproject.org//x/8RkhB.
>>
>> I propose we vote to adopt this timeline.
>
> The motion is seconded (by your chair) and is now OPEN for
> voting. The vote will remain open until 23:59 UTC on Monday,
> August 23, 2010.
>
> NOTE: In the interest of time and given the significant
> previous discussion, the voting period is SHORTER than usual.
>
> As a reminder, this is a public, on-list vote with a "+1"
> signifying "adoption of the 2.8 timeline as proposed."
>
> Per our governance documents, a -1 vote must be accompanied by
> a detailed explanation. A single -1 vote based on a material
> objection will block action. However, -1 blocking votes can be
> overridden by a 2/3 majority roll call vote of active TCC
> members.
>
> Seth
> _______________________________________________
> sakai2-tcc mailing list
> sakai2-tcc at collab.sakaiproject.org
> http://collab.sakaiproject.org/mailman/listinfo/sakai2-tcc
>



-- 
John Bush
602-490-0470


More information about the sakai2-tcc mailing list