Wed Jun 19 12:30:06 PDT 2013
[sending to dev list, but really targeting CLE release team]
Hi CLE release team,
I think our group email address is broken! Probably been broken for a
while. Can someone look into that?
In the meantime, here is the stupid plan I came up with for Sakai CLE 2.9.3
. I have a feeling it is a little aggressive schedule-wise. But see what
you think.
-----------------------
Hi CLE Release team,
Here is my thinking for a CLE 2.9.3 schedule:
- week of June 24 - Merge issues and cut a 2.9.3-rc01
- week of July 1 - Test rc01. If necessary cut an rc02.
- week of July 8 - CLE 2.9.3 production
Scope:
Main purpose of CLE 2.9.3 release is to turn AntiSamy on and a few key
fixes.
* CLE 2.9.3 should have AntiSamy turned on and a handful of issues.
Question - High or Low setting by default? I think if it is turned on now
it would be High by default.
* There are two security issues already fixed and verified. Three security
issues would need verification to get in.
* Several translations are already verified and just need to be merged.
* https://jira.sakaiproject.org/browse/LSNBLDR-227 - was listed as a
blocker issue. Should be easy to include?
* https://jira.sakaiproject.org/browse/KNL-1060 - listed as a critical
issue, already fixed and verified.
https://jira.sakaiproject.org/browse/KNL-1089 - not looking like this
would get done in time based on proposed schedule above?
Thoughts?
Thanks
Neal Caidin
CLE Community Coordinator
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://collab.sakaiproject.org/pipermail/sakai-dev/attachments/20130619/2396cd88/attachment.html
More information about the sakai-dev
mailing list