Thanks Aaron, that's what I originally thought, but those "Affects
Versions" were throwing me off.


On Thu, Dec 6, 2012 at 9:39 AM, Aaron Zeckoski <azeckoski at unicon.net> wrote:

> First - all the UCB changes are in trunk only so if you are
> experiencing issues in 1.4 (which is tagged before any of that work
> was done) then it is unrelated to the UCB work. None of the UCB work
> as been released (at least not that I am aware of) so it and all
> related features are all for future release and only being run by UCB
> currently.
>
> In general I would guess those affects versions are not correct.
> Certainly that is the case for
> https://jira.sakaiproject.org/browse/EVALSYS-1259 since it refers to
> functionality that is not in 1.4.0. Same thing for
> https://jira.sakaiproject.org/browse/EVALSYS-1261.
>
> -AZ
>
>
> On Thu, Dec 6, 2012 at 11:21 AM, Nicola Monat-Jacobs
> <nicola at longsight.com> wrote:
> > Folks -
> >
> > I believe this is related to the EvalSys changes coming from UCB, but
> I'm a
> > bit confused about the JIRAs related to "in progress" notifications. I
> know
> > some work was done here which, I think, introduced a new notification? I
> > remember seeing some notes about some of it getting rolled back? I'm
> > assuming some of these plans are in confluence but I just can't find
> them.
> >
> > Also, looking at the JIRAs makes me more confused:
> >
> > EVALSYS-1259: Affects Version is 1.4.0, Fix version is 1.5.0. But there
> > doesn't seem to be an actual commit here. Okay, maybe its somewhere else?
> >
> > EVALSYS-1261: Affects version is 1.3.0 and fix version is 1.5.0, but
> looks
> > like only commits to Unicon's branch?
> >
> > Basically, when I'm running 1.4.x, what do I have to do to get functional
> > notifications? Do I need some patches from 1.5 or what? Right now we're
> > experiencing EVALSYS-1259.
> >
> > Also, 'available' notifications seem to be going out when the
> notification
> > is created, not when its open (if that date is set to sometime in the
> > future). Is anyone else experiencing this?
> >
> > Thanks,
> > Nicola
> >
> > _______________________________________________
> > evaluation mailing list
> > evaluation at collab.sakaiproject.org
> > http://collab.sakaiproject.org/mailman/listinfo/evaluation
> >
> > TO UNSUBSCRIBE: send email to
> evaluation-unsubscribe at collab.sakaiproject.org
> > with a subject of "unsubscribe"
>
>
>
> --
> Aaron Zeckoski - Software Architect - http://tinyurl.com/azprofile
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://collab.sakaiproject.org/pipermail/evaluation/attachments/20121206/a5b210d6/attachment.html 


More information about the evaluation mailing list