Sam, Aaron and I just completed 2.9.x merge work. The 2.9.x merge backlog now stands at 2 tickets, both of which are being punted to the 2.9.3 release. [1] I think its time to consider cutting 2.9.0-rc01 tag.
I also recommend that from this moment until 2.9.x is released, we limit branch merge work to release blockers and regressions discovered during final testing.
I've started a local build of 2.9.x-all against an empty .m2 repo. If I hit a build failure you'll be the first to know.
Cheers,
Anthony
[1] https://jira.sakaiproject.org/browse/SAK-22798
major, accessibility; merge conflicts, Gonzalo Silverio and Joe Humbert concur that we can punt on this
https://jira.sakaiproject.org/browse/SAK-22521
major, neoPortal sites drawer issue, no trunk commit revision provided despite repeated requests, so punt